List of some completed installations from 2024 with directional drilling and pipe ramming

  • Chris Weatherall
  • Jan 16
  • 1 min read

Updated: Aug 27

Notable High Voltage Electricity duct installations (all pipes SDR 11 Class 1+ Electric Duct)

  • 200m x "Two Way" (225mm and 110mm) at York Show Ground for HACS Construction, by directional drilling

  • Designed and installed 30m x 700mm steel casing installed by pipe ramming, this was to solve unexpected gravel and groundwater causing problems for a previous directional drilling attempt. Once installed, the HDD then transited through this steel pipe, allowing the internal carrier ducts to be installed.

  • 80m x "Four Way" River Crossing by directional drilling, this was for 3 no 225mm and 1 no 110mm ducts, for 132kV cables, which went into the sleeve above.

  • Designed and installed 12 no 70m x 355mm + 125mm installations, through rock, by directional drilling at 3m spacings for 400kV cable diversions beneath a woodland.


Other notable installations

  • SWDD designed and installed a highly complex 120m rising main for Stonebridge Homes, crossing a busy A-Road in Barnard Castle and navigating a safe route through numerous existing services.

  • 400m x 180mm Water Barrier Pipe installations for Port of Tyne in Newcastle-Upon-Tyne, design and install.

  • 70m x 225mm Surface Water road crossing installed by directional drilling for Esh, under the A167 for a housing development.



Reception side, 400kV Ducts, installed by directional drilling
Reception side, 400kV Ducts, installed by directional drilling
Launch side, 400kV Ducts, installed by directional drilling
Launch side, 400kV Ducts, installed by directional drilling


 
 
 